SmartSLD
Template · 10 min read · Updated May 2026

Solar Interconnection Diagram: Template and Examples

Every grid-tied solar installation needs an interconnection single-line diagram before the utility will turn it on. The drawing tells the utility's plan reviewer that your install is safe, code-compliant, and won't backfeed dangerous current onto a de-energized line. Get it wrong and your application bounces; get it right and approval is usually a formality.

This article covers what every interconnection SLD must show, the NEC code clauses behind those requirements, and three worked examples: a residential string-inverter system, a commercial microinverter system, and a hybrid PV + BESS install. Free templates linked at the end.

Open the free editor to draw your interconnection SLD

What utilities require in the SLD

Specific requirements vary by utility (your AHJ may add more), but every utility expects to see the following on the diagram:

  1. Utility service entrance. Voltage, phase, amperage. For residential this is typically 120/240 V split-phase 200 A.
  2. Main service disconnect. Rated breaker or fused disconnect with amperage and AIC rating.
  3. Utility-accessible AC disconnect for the PV system. Visible, lockable, labeled. Some utilities require this even if NEC doesn't (NEC 690.13 only requires a PV disconnect, not necessarily utility-accessible).
  4. Inverter(s). Make, model, AC and DC ratings. UL 1741 SA / IEEE 1547 listing called out.
  5. PV array. Number of modules, module make/model, total DC kW.
  6. DC disconnect. Required between modules and inverter (NEC 690.15).
  7. OCPD (overcurrent protective device). The breaker on the AC side, sized per NEC 705.12 (120% rule for backfeed at the bus, or supply-side connection per 705.11).
  8. Grounding electrode conductor (GEC). Show the bond between the inverter and the grounding system. NEC 690.47.
  9. Rapid shutdown initiator (for rooftop systems). NEC 690.12. Usually a labeled switch at the service entrance.
  10. Labels. Each labeled element should match field labels installed at the equipment. NEC 690.13(B), 690.56.

Example 1: Residential string-inverter PV (8 kW)

The most common configuration: roof-mounted PV array → DC combiner → string inverter → AC disconnect → main service panel backfeed breaker.

Backfeed breaker sizing (NEC 705.60 + 705.12)

Two calculations matter:

1. OCPD continuous current sizing: I_OCPD ≥ 1.25 × I_inverter_continuous

For a 7.6 kW inverter at 240 V: I = 7600 / 240 = 31.7 A, so I_OCPD ≥ 39.6 A → 40 A breaker.

2. 120 % rule for backfeed location: (Bus rating × 1.20) − Main breaker ≥ Backfeed breaker

For a 200 A bus with 200 A main: (200 × 1.20) − 200 = 40 A — exactly at the limit. A 40 A backfeed is the maximum allowed at this bus.

If the math doesn't work (e.g. larger PV system on a 200 A bus), you have three options:

Example 2: Commercial microinverter PV (60 kW)

Microinverter systems replace one big string inverter with many small ones, one per module. The SLD is similar but with these differences:

The interconnection SLD shows one representative microinverter and notes "qty 150 typical" rather than drawing every one. The combiners are explicit. The utility-accessible AC disconnect is between the combiner output and the service.

Example 3: Hybrid PV + BESS (480 V three-phase, 100 kW PV + 250 kWh battery)

Battery-tied systems are increasingly common (utility rate arbitrage, demand-charge mitigation, backup power). The interconnection SLD adds:

This is the same topology shown on the SmartSLD homepage demo — utility service → main → meter → 480 V switchgear, with a PV inverter on one branch and BESS on another via a bidirectional converter. Open the demo to see it live.

Use this template — open in SmartSLD with one click

NEC clauses to cite on your drawing

The plan reviewer wants to know you've thought about the code. Putting these annotations on the diagram itself reduces back-and-forth:

Common reasons utilities reject interconnection SLDs

Templates

Open any of these in the editor and modify for your specific install:

The homepage demo at smartsld.com is the hybrid template. Use the AI prompt feature to generate a variation tailored to your system size.

FAQ

Do utilities accept SLDs drawn in any software?

Most accept any clean, readable format — PDF, PNG, or DXF. A few large utilities have specific format requirements (PG&E, ConEd). Check your utility's interconnection application portal first.

Do I need a PE stamp on my interconnection SLD?

Depends on the utility, system size, and state. Most residential systems under 25 kW don't require PE stamping. Larger or commercial systems often do.

What about microgrid interconnection?

Microgrid interconnection adds an ATS, critical-load distribution, and possibly islanding controls. The SLD becomes more complex but the same component rules apply.

Can AI generate an interconnection SLD for my specific system?

SmartSLD's AI agent can. Prompt example: "8 kW residential PV with single-phase string inverter, 30 A AC disconnect, 40 A backfeed breaker, 200 A main service" generates the full SLD with NEC-compliant labeling. Cross-check the output against your utility's checklist before submitting.

Related


Got a utility rejection because of something we didn't cover? Send it to [email protected] — we'll update the article.